Routing + resource in business central

Posted on by

Hi All

I need some guidance on how I can handle this manufacturing data in BC.

I got a list of production orders with an item (in this case Item = PRD 1)

1. each order has a list of operations for this item, but for each order the routing(operation steps) change, as you can see for some pro orders there are 3, some 4 or 1.

2. But an Item master can be assigned with a single routing code containing constant steps. How an item with changing operation steps can be handled in BC??

3. Also resource was assigned to the production order line, with a different resource for each operation step. The Operation steps and resource combination also change. How I can capture resources in production order for each operation step/routing???

pastedimage1677483154218v1.png

  • Suggested answer
    Andy Sather Profile Picture
    Andy Sather on at
    RE: Routing + resource in business central

    Hello,

    If you don't get further responses to this issue, you may want to raise a support request to Microsoft support via your CSP / Partner.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Community AMA December 12th

Join us as we continue to demystify the Dynamics 365 Contact Center

New! Quick response templatesâš¡

Save time with the new custom templates!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,228 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,056 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans