In the costing sheet, I added some indirect cost with type as Rate and absorption to the process (Route process).
When I estimated the batch order Estimated Consumption in the Process and Indirect costs are same (in hours) - Both are 2 hours
But, when I report as finished, there's a huge difference in the Estimated consumption and realized consumption of Indirect costs. After some analysis I found that Realized consumption is a sum of the Process Hour of FG and SFG.
For Example,
SFG Process hour is 1
FG Process Hour is 2
SFG Indirect cost realized consumption is 1 (which is correct)
FG Indirect cost realized consumption is 1+2 (Which is sum of process hours of SFG and FG)
Expected result for me is to have the Indirect cost realized consumption calculated based on the process hours of Current batch order and not based on the sum of FG & SFG Process hours.