Announcements
I have an item setup to be lot controlled
On the item tracking code, I have it set to require an expiration date
I DO NOT have require expiration date entry checked
I DO NOT have Strict Expiration Date checked
I have 1Y in the calculation.
I do a purchase order. Upon receipt, a lot number needs to be assigned - however, no expiration date is being calculated. I am having to enter it manually.
What am I missing to get this to calculate?
Also, does it use the posting date as the base point for the calculation - in this example - posting date + 1Y
Thanks
Thank you - this was the answer
Hi,
I tested it with the following set up:
When you then create a purchase order and check the tracking lines, it is right, that the experation date is not calculated:
Because the expiration date will be calculated during posting of the purchase order.
The calculation is based on the document date.
You have the "Use Expiration Dates" checked i assume? You did not mention that field explicitly or maybe you just used another name for it.