web
You’re offline. This is a read only version of the page.
close
Skip to main content

Announcements

No record found.

News and Announcements icon
Community site session details

Community site session details

Session Id :
Finance | Project Operations, Human Resources, ...
Suggested Answer

Run project status report

(0) ShareShare
ReportReport
Posted on by 30

We have tried to run a status report for a project, but currently are no options available for that. (see screenshot)

Do you have the possibility to create a status report in your environment?

Are there some settings in backround we have to change or activate? How can we create a report in Project Operations?

Screenshot_5F00_run-report.jpg

I´m looking forward to your answeres. Thanks you!

Patrick

I have the same question (0)
  • Olena Volodymyrivna Profile Picture
    29 on at

    Hi Patrick,

    Did you resolve this issue?

    I think that you need to configure the Power BI reports.

    Best regards,

    Olena

  • Patick Profile Picture
    30 on at

    Hi Olena,

    is there a guidline available how to configure them?

    Or how can i do that?

    Best regards

    Patrick

  • Winters Profile Picture
    155 on at

    Hi Patrick,

    Not sure if this will help but it might be a starting point for you.

    github.com/.../Project-Power-BI-Templates

    docs.microsoft.com/.../connect-to-project-for-the-web-data-through-powerbi-desktop

  • Chuck McBride Profile Picture
    5 on at

    Hi Leon,

    Thanks for the information that you provided.  This is really good stuff, but it doesn't address the initial request (which I am looking for the answer as well) of what does the Status Report give you within Project Operations?  

    Thanks,

    Chuck

  • Patick Profile Picture
    30 on at

    Hi Leon,

    thanks for the answere - it helps a lot.

    I got some informations from colleagues that you can create a SSRS document (old way) or do it with Power BI. Microsoft don´t push these report features to export some data, supposedly they want to keep the user in the app and let them work with dashboards.

    Our solution will be - create a Power BI Dashboard. 

    BR

    Patrick

  • Suggested answer
    Matthew Lazowski Profile Picture
    3,163 on at

    Unfortunately there are no Project Status reports in vanilla Project Operations. Some PPM apps available for Dataverse include that feature they would need to be installed on top of Project Operations.

  • Patick Profile Picture
    30 on at

    Hi Matthew,

    do you have some examples or recommendations for such apps?

  • Winters Profile Picture
    155 on at

    Hi Patrick,

    This is not tested as such and it is for PSA but PO has a lot of PSA parts in it.

    You can create a power automate that gets all the information required then push it to Power Bi.

    www.campana-schott.com/.../more-power-for-ppm-use-case-dynamics-psa-status-reporting

    Not a solution as mostly needs to get built. hope it helps.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 545 Super User 2026 Season 1

#2
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 408

#3
Adis Profile Picture

Adis 267 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans