RE: May I know how do we define Scrap % and Routing Link Code in Navision 2018?
Josh,
Adding to YUN's reply... You should have the handouts I sent over on the common topics you have been asking on.
Scrap % appears on the Production BOM, Item Card, and Routing line. On the Production BOM if I need 10 units and had a a scrap percentage, the Component demand will take the 10 and add the scrap factor so you pull the correct units.
The Routing Link Code ties Production BOM components to the actual Routing Line Operation step so you can pick and consume the correct components in the correct operation step.
If you need me to resend the handout tell me.
Thanks,