Hi,
My accounting currency is USD.
I created a PO in project accounting in Canadian dollar in the amount of CAD1,000 dated Aug 10, 2020.
The last exchange rate in the setup USD-CAD is 95.23809 dated Feb 2020, so I'm expecting that the total amount in USD is USD952.38 which can be viewed if you click Totals in PO.
But when I click Project budget status in PO>>Line details>>Financials>>Project budget status, the system uses different exchange rate which is the old exchange rate dated Dec 2013.
The system also updated the Remaining budget based on the old exchange rate which is wrong.
Pls see attached screenshot that shows the discrepancies.
Is this a bug or is there an explanation for this?
Thank you.