Update several calendars at once with closing days

(1) ShareShare
ReportReport
Posted on by 57

Hello all

I am currently working on a request with calendars (Organization administration). The requirement is that all relevant calendars must be updated with an additional closing date. So we have several calendars that are already defined and in use. Now we want to update all calendars with additional closing days.

Is there any way to do this with something like a job or is it necessary to do this manually for each calendar?

Thank you in advance for any kind of feedback!

Regards

Fabian

I have the same question (0)
  • Suggested answer
    André Arnaud de Calavon Profile Picture
    301,187 Super User 2025 Season 2 on at

    Hi Fabian,

    How many calendars and days do you need to update? There is an option to use the Data management export and import for this. There is an entity "Working times" which can be first exported, adjusted, and then imported. I was not able to find a public entity for this which would allow you using the Excel add-in.

  • Suggested answer
    Mohit Rampal Profile Picture
    12,565 Moderator on at

    Hi Fabian, We have created a custom data entity for working times as below, let me know if you need any help.

    pastedimage1683078134853v1.png

  • FabianIBK Profile Picture
    57 on at

    Thank you for your feedbacks, I will check with the customer whether using data management framework can support the update.

    Regards

    Fabian

  • Suggested answer
    Gaurangkumar Jani Profile Picture
    4,534 User Group Leader on at

    Hi FabianIBK

    How do you normally update the calendar? Are you using base calendar?

    I have done some similar configuration for my client where they wanted to do integration from external system to FO for leave to be updated for PMA Resource availability, so we created all different calendar for each user but keep one base calendar to update mass leave / closing and for individual we are updating main calendar control field.

    Please let us know if this helps.

    Thanks

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Laurens vd Tang Profile Picture

Laurens vd Tang 307 Super User 2025 Season 2

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 123 Super User 2025 Season 2

#3
Gerardo Rentería García Profile Picture

Gerardo Rentería Ga... 67 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans