Hi there,
We have a requirement where we needed to auto update the start date of a project task based on other Project's finish date. We were able to achieve this functionality using Schedule APIs. While developing this, i realized that there is a limit on open operation sets for user.
Does anybody know how to close an oprationset as it completed the execution?
Thanks,
Venu
Hi,
I tried to change the maximum number of OperationSets, but it can't be changed.
This official documentation clearly states this Limitation:
https://docs.microsoft.com/en-us/dynamics365/project-operations/project-management/schedule-api-preview#limitations-and-known-issues
The official document does not provide a method to close the OperationSet, please test whether it can be closed automatically after all operations are performed.
If this helped you, I'd appreciate it if you'd mark this as a Verified Answer, which may in turn help others as well.
Best Regards,
Frank Gong
Moving this to ProjOps forum.
Vallamreddy VenuGopal, , excess OperationsSets can be abandoned by calling the msdyn_AbandonOperationSetV1 action. There's also a recurring could flow Project Service Core - Abandon Open Operation Sets that does this on a recurring schedule. Normally all you need to do is execute an operation set with msdyn_ExecuteOperationSetV1. See here for more info:
daytodaydynamics365.com/.../
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Martin Dráb 664 Most Valuable Professional
André Arnaud de Cal... 522 Super User 2025 Season 2
Sohaib Cheema 303 User Group Leader