How set priority for Replenishment work

(4) ShareShare
ReportReport
Posted on by 77
Hi All, I have three work templates for Replenishments A, B and C. All are using min/max replenishment type. Template A contains item which should be priority 1 followed by B and C. I need to assign priority so that replenishment happens as per set priority and on the mobile device they should appear in the priority sequence.
 
Under work template we have to assign work priority but what else setup do I need to achieve this?
  • Suggested answer
    Sagar Suman Profile Picture
    6,191 on at
    How set priority for Replenishment work
    Hi,
    Once work priority is set on the work template and its filtering items the next step is to work on the mobile menu items 
    Option 1 - Use work list and use the query sorting to sort work on work priority. This way work with priority 1 are shown earlier than priority 2 and so on. 
    Now when you go to mobile device 
     

    Option 2 - Use system directed work and use the query to sort based on work priority. 
     
     

    Now when you login in the mobile device system will first ask worker to work on all priority work 1 and only after all priority 1 work are finished priority 2 are given and so on. This option is better for strict implementation of priority but lacks flexibility and overview. 
    Below is the pick location of work with priority 1. 
     

    Option 3 - You can use grouping option. This way worker gets a chance to enter the priority of work he enters to work and after that system assigns all the work. 
     
  • Suggested answer
    Laurens vd Tang Profile Picture
    2,635 Super User 2025 Season 1 on at
    How set priority for Replenishment work
    Good day,
     
    I believe the best way to achieve that is by setting up product filter codes. 
     
     
    You can connect a product filter code to a released product
     
     
    Three work templates for replenishment with the work priority need to be configured
     
     
    On each work template you need to set up query and a join to the warehouse item number
     
     
     
     
     
    Dynamics will automatically apply the priority during the work creation. 
     
     
    Best regards,
    Laurens van der Tang
  • Suggested answer
    Holly Huffman Profile Picture
    5,985 on at
    How set priority for Replenishment work
    Hi there! Good morning, evening, or afternoon - depending on where you are :) Hope you are well today!
     
    • To set up the priority-based replenishment sequence and ensure it appears correctly on the mobile device, follow these steps in Dynamics 365 Supply Chain Management:
    • 1. Assign Work Priorities in Work Templates
      • You’ve already assigned work priorities in the work templates (A, B, and C). Make sure the priority values reflect the desired order (e.g., A = 1, B = 2, C = 3). Lower numbers represent higher priority.
    • 2. Configure Location Directives
      • Ensure location directives are correctly set up for the replenishment process. The location directives determine which inventory locations are replenished, and they need to align with the work templates.
      • Check that the “Sequence Number” in location directives matches the replenishment priority you’ve set for each template.
    • 3. Set Up Mobile Device Menu Items
      • In Warehouse Management > Setup > Mobile Device > Mobile Device Menu Items, ensure the menu item associated with replenishments points to the correct work templates.
      • Enable sorting based on Work Priority for the mobile device setup. This ensures that work appears in the specified priority order.
    • 4. Enable Work Priority Sorting in Mobile Device
      • Go to Warehouse Management > Setup > Work > Work User Setup for the relevant users.
      • Enable sorting of work based on Work Priority. This ensures that work assigned through the mobile device appears in the defined sequence.
    • 5. Test the Setup
      • Create test scenarios with replenishment requirements for items in templates A, B, and C.
      • Verify on the mobile device that work appears in the correct priority order (Template A first, then B, and finally C).
    • 6. Additional Configuration (if needed)
      • If the system isn’t following the expected order, check the Wave Templates if you’re using waves to process work. Make sure the wave processing sequence is configured to respect work priority.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Understanding Microsoft Agents - Introductory Session

Confused about how agents work across the Microsoft ecosystem? Register today!

Jonas ”Jones” Melgaard – Community Spotlight

We are honored to recognize Jonas "Jones" Melgaard as our April 2025…

Kudos to the March Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 294,459 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 233,066 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,158 Moderator

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans