Hello All,
We are using Project module (Investment Project) feature to Implement the assets under construction concept.
Steps we follow
1) Create an Asset.
2) Create an Project.
3) Make project transactions (Project purchase orders and project expense journals)
4) Post the Project estimate.
5) Eliminate the Estimate.
Question:-
=========
Step no.4 only captures the amount of PO's that are invoiced, It doesn't capture the Product receipts.
Is there any setup in the system which will take into consideration the Product receipts as well while posting the Estimates?
Thanks, Kaushik
*This post is locked for comments