I have the following 3 scenarios. Would request a setup that need to be done:

Scenario - A:

Date Demand Sales Order Qty For a Single Item MRP Re-Run Values
01-Jan-2018 150    
13-Jan-2018   70 80
15-Jan-2018   5 75
20-Jan-2018   25 50
27-Jan-2018   50  
01-Feb-2018 200    
04-Feb-2018     200
01-March-2018 250    
01-April-2018 200    

In the above data:

a. The Demand has been Manual entry in the Master Planning

b. The Sales Order Quantity are different Sales Orders are created for the same item in different dates .

c. MRP Re-Run is the Master Planning being run in the defined dates.

Configuration Done:

1. Reduction Key method used in Master Plan : "Transactions - reduction key"

2. Coverage Group : Reduce Forecast By : Orders

Problem faced:

a. The MRP Rerun values at 13-Jan-2018 showing 80 but when we are re-running MRP on 15-Jan-2018 , the values are not considering the total sales orders quantities i.e. 70+5.

b. Similar problem is perceived in the consecutive MRP - Re run dates.

Would request if I am missing anything .......

___________________________________________________________________________________________________________________

Scenario - B:

Date Demand Sales Order Qty For a Single Item MRP Re-Run Values
01-Jan-2018 150    
13-Jan-2018   70 80
15-Jan-2018   5 75
20-Jan-2018   25 50
27-Jan-2018   25  
01-Feb-2018 200    
04-Feb-2018     225
01-March-2018 250    
01-April-2018 200    

Configuration:

Same as above

Problem Faced:

1. When I am running the MRP for 04-Feb-2018 , it is not considering the value it is mentioned. Is there any configuration missing.

I am running the MRP on 12-Jan-2018 simulating the sales orders with the shipping dates and quantity as mentioned 

_________________________________________________________________________________________________________________

Scenario - C:

Date Demand Sales Order Qty For a Single Item MRP Re-Run Values
01-Jan-2018 150    
13-Jan-2018   500 0
01-Feb-2018 200   0
04-Feb-2018     0
01-March-2018 250    
03-March-2018     100
01-April-2018 200    

Configuration:

Same as above

Problem Faced:

1. When I am running the MRP for 03-March-2018 , it is not considering the value it is mentioned. Is there any configuration missing.

I am running the MRP on 12-Jan-2018 simulating the sales orders with the shipping dates and quantity as mentioned 

*This post is locked for comments

I have the same question (0)
  • Weaveriski Profile Picture
    23,620 Moderator on at

    You would need to post net requirement screen shots to see.

    MRP will not consider demand in the past that is a forecast, so it depends what your "Demand" entered in MRP is. It will consider outstanding Sales orders. I am not sure which part of the demand you mean when you say "it is not considering the value it is mentioned".

    MRP you should be planning forward, so move all of your demand forward and plan as though it is in the future to understand, trying to work out what you should have done is harder.

  • Community Member Profile Picture
    on at

    Hi Steven,

    Please find the screenshots as:

    a. Net Requirements :

    Open-Sales-Orders.png

    b. Open Sales Orders:

    Open-Sales-Orders.png

    c. Manual Demand Inserted:

    Manual-Demand.png

    According to the manual demand , the requirement is 150 . The sales orders quantities are 100 ,5 and 25. Now the reduction key is set to orders so the plan should have shown 20 instead of 75. In the master plan the reduction principle is set to Transaction - reduction .

    Am I missing any configuration . Please suggest.

  • Weaveriski Profile Picture
    23,620 Moderator on at

    Your net requirements are not showing the sales orders - why not?

  • Chandra Wijaya Setiawan Profile Picture
    1,145 on at

    You have configuration inventory dimension but I don't see it on sales line . Could it be the configuration value are different?

    You should run net requirement from sales line instead of item master to try where the sales line hit to master planning

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
CP04-islander Profile Picture

CP04-islander 16

#2
GiacomoRovai Profile Picture

GiacomoRovai 4

#3
Douglas Noel Profile Picture

Douglas Noel 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans