Dynamics SL 7.0 FP1 & MSP 2007
Is the SL - Project Server Connector able to sync the Timesheets or actual job information?
We can configure it to sync projects and tasks, even resourses, but we can´t find any information about next steps.
What about time entry?
It must be done on SL, MSP or bidirectional?
It will sync the advance of the project?
Any information, guide, tuto will be appreciated.
*This post is locked for comments
Hi, it does sync actuals, if resources have been assigned to an integrated task. This is automatic, but in Project Tak Updates still need to be accepted.