Answered

Cannot release status from Started to Created

(0) ShareShare
ReportReport
Posted on by 355

Hello Everyone!


Looking for someone who could provide us the help on how to fix encountered issue for a specific production order.


There was a created production order where status was already set to Started but unfortunately the production is now has to be deleted.


The production order has no any posted Pick list, Route and RAF.


When we tried to reset status into Created below is the error we received and multiple RAF journals were also posted.

0218.error-log.jpg

Many thanks for the help.

I have the same question (0)
  • Dhanicca Macatangay Profile Picture
    355 on at

    For additional information, before we reset the status to created the status of the Production order is already set to Reported as finished.

  • André Arnaud de Calavon Profile Picture
    304,538 Super User 2026 Season 1 on at

    Hi Dhanicca,

    You used the tag AX2012, but posted the question in the Dynamics 365 Finance question. Is the question related to AX2012? Your question is in the wrong forum, we will fix that based on your reply.

    Anyway, is this the only production order having this issue? Can you reproduce this in a separate environment? Try to do a full x++ compilation and CIL build to see if it fixes the issue.

  • Dhanicca Macatangay Profile Picture
    355 on at

    My apology for the incorrect tagging. This is an AX 2012 issue. I was just have trouble finding AX 2012 and to proceed with my query I just tagged it as Dynamics 365 Finance.

    We already encountered this issue to numerous production orders just this day. Shall we still proceed with the compilation or there is other way to fix the issue?

    Thank you very much for the response.

  • Dhanicca Macatangay Profile Picture
    355 on at

    Yes, we were able to reproduce it in our test environment.

  • Verified answer
    André Arnaud de Calavon Profile Picture
    304,538 Super User 2026 Season 1 on at

    Hi Dhanicca,

    In between your post got moved to the correct forum, I noticed.

    Can you try the compilation and build in this test environment first? The use of AXbuild.exe is faster compared to start the x++ compilation in the development workspace.

  • Dhanicca Macatangay Profile Picture
    355 on at

    Thank you, André, for that quick response.

    We'll do the above on our environment and revert on this forum for the result.

    Again, thank you.

  • Dhanicca Macatangay Profile Picture
    355 on at

    Hi Andre,

    We tried the suggested action to correct the above issue but we can't still proceed to reset the status of the production order into created. Our developer said that the items involved in the production orders should already be investigated.

    Thank you for sharing your idea with us.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 689

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 606 Super User 2026 Season 1

#3
CP04-islander Profile Picture

CP04-islander 356

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans