Is it possible to make inventory adjustments moving purchased items from one project to another?
Is it possible to make inventory adjustments moving purchased items from one project to another?
Hello,
Once you do an Inventory transfer to move an Item onto a Project, we consider it consumed so it wouldn't be available to be transferred. However, you could do a Project Inventory Return to back it out of the Project, then the quantity would be available again to transfer over to the other project.
Project Inventory Returns are processed under the same window as Project Inventory Transfers. (Project > Transactions > Inventory Transfer) You just need to select the Transaction Type of Return in the upper left.
I hope this helps!