I have entered the original budget schedule for a project using multiple workstreams and account categories and want to duplicate those entried in teh EAC schedule and maintain changes there. How can I do this in the fewest steps possible?
*This post is locked for comments
Thanks, Carolyn. I do not appear to have access to the Transaction Import function. However, I appreciate the answer.
Hi Mike,
Unfortunately, it is a very manual process. There is no copy functionality from the Original Budget Schedule to the EAC Schedule. You could try and use Transaction Import to import the EAC schedule. Let me know if you have additional questions.