We have a workflow where a requisition submitted to workflow aims out to Power Automate, which gets approval and then confirms its conversion into a purchase order.
Today (17th March 2021), we created a brand new requisition. Got it approved. Requisition confirmed and PO duly generated - but with different dates output to SSRS. The PO delivery date is set correctly to 17th March 2021, but the PO date in the PO header is set to 18th December 2020 (btw, in the example XML generated, the dates are UK way around - dd/mm/yyyy).
Looking at the req, Requested Date, Accounting date, Created Date, Modified Date, Submitted Date are all 17/03/2021. Similarly line Requested Date, Accounting Date both 17/03/2021
On the resulting PO:
<Field_DeliveryDate>17/03/2021</Field_DeliveryDate>
but
<Field_PurchOrderDate>18/12/2020</Field_PurchOrderDate>
Any idea where the 18th December 2020 date could be coming from?
Ian W.