Hi,
I'm using ax 2012 R3.
I have a situation in my production where I'm using some raw material in No for consumption and the balance of the raw material I need to get into the system as sqm or meter.
I tried unit conversion to set item A 1 no= 3sqm, item B 1 no =6 meter. the issue is in the picking list I cannot consume item A below 1.5sqm. and the same way item B below 3 meters.