Cannot Change Status from Released Production Order to Finished Production Order

(0) ShareShare
ReportReport
Posted on by 2,560

Hi all,

I met an error below when I change status of Production from Released to Finished. In addition, actually I did reverse the Consumption and Output Quantity. Is it affect on change status? How and why to get this error occurred? How can I solve this problem? 

Thousand thanks for any help.

Warmest Regards,

Shin

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Community Member Profile Picture
    on at

    Hi Shin

    You have to complete all your process as required after that it will be chnage into finished.

  • Vanessa Shin Profile Picture
    2,560 on at

    Hi Sandeep,

    First of all, Thanks for your replied.

    Meanwhile, may I know what required process that you mentioned above?

    Further, may I know why system do not allow change status?

    Warmest Regards,

    Shin

  • Community Member Profile Picture
    on at

    Output entry against line no 10000 should be post.

  • Verified answer
    Miguel Llorca Gómez Profile Picture
    7,019 User Group Leader on at

    Register any output, from production journal or from output journal. You don't need to finish it at all. By the way...which version are you using?

    Good luck!

  • Vanessa Shin Profile Picture
    2,560 on at

    Hi Sandeep,

    Thanks for your help.

    Warmest Regards,

    Shin

  • Vanessa Shin Profile Picture
    2,560 on at

    Hi Miguel,

    First of all, thanks for your advice.

    Actually it is NAV version 5.0. I'll try and find out your method.

    Warmest Regards,

    Shin

  • Verified answer
    Aleksandar Totovic Profile Picture
    16,765 on at

    You cannot change status of PO to finished if you have not any output entry. If you post reversed entries, I suppose, your output is 0. Register any output on this PO. I suggest to post 0,001 as output and change status to finished. After that, you can post Negative Adjmt. for thus item using Item Journal.

    Once again, you cannot change status of PO to finished if you have not positive output entries.

  • Vanessa Shin Profile Picture
    2,560 on at

    Hi Aleksandar,

    Can I ask you another question? If both Consumption & Output was reversed to Zero, will system allow to change status to Finished?

    Best Regards,

    Shin

  • Suggested answer
    Aleksandar Totovic Profile Picture
    16,765 on at

    No, system doesn't allow this. You have to have ate least one entry for output. Consumption isn't important.

  • Vanessa Shin Profile Picture
    2,560 on at

    Hi Aleksandar,

    Thousand thanks for your help.

    Warmest Regards,

    Shin

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > 🔒一 Microsoft Dynamics NAV (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans