Hi Experts,
I have a question concerning multilevl production orders.
Here the simple test I did on CRONUS database :
I have created 4 production orders called:
- NAVOF-00
- NAVOF-01
- NAVOF-02
- NAVOF-03
With the followwing caracteristics
NAVOF-00 has only one component which is NAVOF-01 (WO) : Routing : time : 2 h Wait time : 48 h
NAVOF-01 has only one component which is NAVOF-02 (WO) Routing : time : 5 h : wait time : 48 h
NAVOF-02 has only one component which is NAVOF-03 (Item) Routing : Run time : 4 h wait time : 48 h
When I run the planning the planning worksheet, I get the following result :
I dont understand why NAVOF-01 and NAVOF-02 have an ending hour at 16:00
The total duration of the tasks are correct (run time + wait time) and the "wait time" is out of calendars, which is corretc, but why NAVOF-01 does't ends at 14:00 and NAFOF-02 at 11:00 ?
It looks like as if Navision doesn t not calculate at the "hour" level but only at the "day" level".
Have have spent hours on this problem and i have't found any reason why I have this result.
Thanks a lot for your help and support,. in advance :-)
Best Regards,
Jérôme