a couple of items on setting up routing data
1 - where do you identify the number of operators? the work center can be staffed with 1, 2 or even 0.5 operator - wanting to setup to easily identify and correctly cost.
2 - in a process that produces more than one unit - ie, 2 cavity mold produces 2 units; 4 cavity mold produces 4 units - how to identify as the process cycle is on the injection but the quantity produced could be adjusted depending on the cavitation
Thanks in advance.