OPEN MAINTENANCE SCHEDULE LINES

(2) ShareShare
ReportReport
Posted on by
How is the expected start date on open schedule lines calculated for counter (KM) based plan lines
  • Suggested answer
    OPEN MAINTENANCE SCHEDULE LINES
    Hi,
     
    I assume it's Asset Management in D365 F&O.
    The start date on depends on the configured interval type in the maintenance plan.
     
    For a list of different start date calculations, look at this table: Maintenance plans - Supply Chain Management | Dynamics 365 | Microsoft Learn

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Congratulations 2024 Spotlight Honorees

Kudos to all of our 2024 community stars! 🎉

Meet the Top 10 leaders for December

Congratulations to our December super stars! 🥳

Start Your Super User Journey

Join the ranks of our community heros! 🦹

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,703 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,433 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans