We are testing D365 Project Ops, it is not fully configured. A simple question - is it possible to mark the question as completed by the Project Manager irrespective if timesheets or effort were submitted? So it would visually look conducive of being finished?
Yes, in D365 PO, a Project Manager can manually mark a task as "Completed" without relying on timesheets submission.
Thanks
Affan
If my suggested answer has helped, please mark it as verified.