Calculating WIP using Percent of Completion of Job Total

(0) ShareShare
ReportReport
Posted on by

We would like to use the Calculate WIP function in Business Central. We've set up the Job Posting Group accounts and selected Percent of Completion as our WIP Method. Unfortunately, when we Calculate WIP the recognized revenue is wrong. For the job shown below, the recognized revenue is $0 even though the 'percent complete' of the Job is not 0%.

pastedimage1653602985797v1.png

It appears that this is because the WIP is being calculated per task line and then summed for the entire job. Therefore, task 060.00 is 0% complete and none of its billable amount is recognized while the tasks that do have a completion value have no billable total price, and therefore recognize no revenue.

Is there a way to make the WIP calculate on Job Totals rather than per task?

I have the same question (0)
  • Suggested answer
    S.Kawamura Profile Picture
    1,530 on at
    RE: Calculating WIP using Percent of Completion of Job Total

    Hi,

    You described "We've set up the Job Posting Group accounts and selected Percent of Completion as our WIP Method."
    But the screenshot tells us that the job task lines are set as "Sales Value" WIP Method.
    pastedimage1654042283934v1.png

    Job card has a field "Job WIP Method" in Posting tab.
    pastedimage1654042574256v2.png

    And each job task lines also have "JOB WIP Method". Once you have created the job and specified the WIP method on the job card, the WIP method on the job task line is blank.
    pastedimage1654042660459v3.png

    And the WIP method of a job task line can have different values for each task line. Note: Change the WIP Total to "Total" before changing the WIP method.

    pastedimage1654042790496v4.png
    Perhaps change the WIP method for all job task lines to POC, as shown in the figure below, or...
    pastedimage1654042917534v5.png

    set WIP Total and WIP Method to blank and this job's WIP will be calculated by POC method.

    I once did a job WIP survey with similar questions and posted blog.
    Tips & Tricks of JOB WIP Calculation | IT長のネタ帳 (d3654.be)

    I hope this helps you.

    S.Kawamura

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 3,377

#2
Jainam M. Kothari Profile Picture

Jainam M. Kothari 2,696 Super User 2025 Season 2

#3
YUN ZHU Profile Picture

YUN ZHU 1,512 Super User 2025 Season 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans