Workflow Approvals going to multiple department owners

(1) ShareShare
ReportReport
Posted on by 2

We require workflow to go to the department owner from the financial dimension "department" in the PO header.

pastedimage1612766892497v1.png

We have set this up in the workflow

pastedimage1612766964481v4.png

pastedimage1612766984960v5.png

Unfortunately if the lines have different departments it will send the workflow to multiple department owners.

pastedimage1612767072836v7.png

pastedimage1612767085199v8.png

Does anyone have any suggestions to make the workflow ONLY go to the department owner in the PO Header?

Thanks

I have the same question (0)
  • Verified answer
    MATTGUO Profile Picture
    22,351 Moderator on at

    Hi Simon,

    The expenditure participants will retrieve all users in PO lines instead of the PO header. It should not meet your requirement.

    The alternative solution is to use multiple conditions of the department financial dimension in header to select the approver.

  • Michal Krejza Profile Picture
    Microsoft Employee on at

    Hi Simon,

    You haven't mentioned that, but I assume you are using line level workflow in your scenario. When you use line level workflow and Expenditure participant > system will really use dimensions from lines and assign to Dimensions owners from line. 

    The suggestion recommended by Mat will work, but basically you duplicate Dimension owner setup in workflow. I would rather recommend to use Expenditure participant in Purchase order header workflow - this will create one work item for Department owner from header, and it is up to the user to review all lines. In my opinion it is better to have one work item for such a job, rather than 10 work items for each line. But all depends on your business needs.

  • Suggested answer
    simonsmith101 Profile Picture
    2 on at

    Thanks

  • simonsmith101 Profile Picture
    2 on at

    Hi Michal,

    No the workflow is  not line level approval. It looks at the department in the header but then if there are multiple lines with different departments it will send the WF to the owners for the lines NOT just the header. What you suggest is exactly what we are trying to achieve but unfortunately its sending it to multiple department owners .

    Thanks again Simon

  • simonsmith101 Profile Picture
    2 on at

    Hi Michal,

    No the workflow is  not line level approval. It looks at the department in the header but then if there are multiple lines with different departments it will send the WF to the owners for the lines NOT just the header. What you suggest is exactly what we are trying to achieve but unfortunately its sending it to multiple department owners .

    Thanks again Simon

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 689

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 606 Super User 2026 Season 1

#3
CP04-islander Profile Picture

CP04-islander 356

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans