Hi All,
I have a question regarding the requirements date in net-requirements. is it possible to have a safety margin for how AX calculates the requiremetns date? For example, if there is an item requirement that exists for 5th of January is it possible that AX brings ahead the requirement date by say,4 days and generate the planned order on the 1st of January, but the actual requirement date does not change from 5th January.
i tried the issue and receipt margin but it only pushes the actual requirement dates by the number of days you mention in the Receipt margin parameter in the coverage group setting.
Any advice would be appreciated