Hello,
I have a production order in "started" status that I won't be able to finish in time due to an unplanned raw material shortage. What is the recommend way to "delay" this order and thus push out the End Date on the order while maintaining the original start date? Our sales order allocation system keys off of the production order end date, which is why having an accurate date is important.
Current state:
Status: Started
Start date: 11/23/2015
End date: 11/30/2015
Desired state:
Status: Started
Start date: 11/23/2015
End date: 12/15/2015
Thanks!
Tom