I have the message error :   
Calendar 'XXXXX' in company 'XXX' earliest working date is setup on 1/1/2015 which is later than the requested end date . Please contact your system administrator to extend the dates of the calendar.
  • Suggested answer
    Hana Xue Profile Picture
    Hana Xue Microsoft Employee on at
    Calendars
    Hi,
    What actions did you take to cause this error? If you are currently Terminating an employee and this caused you to get this error, you can check this link: The details of the issue 650776 (dynamics.com)
    Best Regards,
    Hana

Helpful resources

Quick Links

Replay now available! Dynamics 365 Community Call (CRM Edition)

Catch up on the first D365 Community Call held on 7/10

Community Spotlight of the Month

Kudos to Saurav Dhyani!

Congratulations to the June Top 10 community leaders!

These stars go above and beyond . . .

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 287,914 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 225,549 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,148

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans