Hi experts,
We need some input/advice related to CTP & assemble-to-order items in Business Central.
We're testing on Cronus, with the assemble-to-order item 1925-W, components BOM (1920-S & 1968-s), components have a lead time of 10D purchase, are critical, and have no sufficient stock for the location. Customer shippning time is 2D
Now when we create a sales order, we expect the lead times to purchase the components to be taken into account when doing the CPT run, however, the systems just proposed the planned delivery date as SHIPMENTDATE (today) + shipping time (2D) = 17/06
Are we overseeing something? Or doest the CPT just doesn't take the purchasing lead time of the components of the assembly item into account?