Microsoft Dynamics AX (Archived)

Estimates for Fixed Price Prices ( with multiple Sub Projects )

(0) ShareShare
ReportReport
Posted on by 373

I have a question primarily about the "estimate" process in Dynamics AX, I have the following project structure:

  1. Master Project
    1. Sub Project 1
    2. Sub Project 2

Hours forecast is recorded on the lower level as illustrated below:

  1. Master Project
    1. Sub Project 1  - Hour Estimate: 3000 USD
    2. Sub Project 2  - Hour Estimate: 6000 USD

Expense forecast is recorded on master level as illustrated below:

  1. Master Project - Expense Estimate : 1000 USD
    1. Sub Project 1 
    2. Sub Project 2 

On the project budget, the forecast above is imported to control budget on both; parent and sub project levels.

On Account Transactions

The on account transaction is filled out on the master project ( parent ) on which invoices will be issues

  1. Master Project - On Account Transactions ( 7000 USD for Milestone 1, and 8000 USD for Milestone 2 )

Transactions :

As the project starts, hours are recorded on the sub project level, the following two hour journals are posted to record actual hours.

 

  • Sub Project 1  | Actual Hour 2000 USD
  • Sub Project 2  | Actual Hour 2000 USD

Invoice Proposal

An invoice is posted on the master project for the milestone 1, for 7000 USD.

Question

When running the first estimate, here are the calculated values:

  • Sub Project 1 |   Cost to complete method is "Total Budget - Actual"

Total Cost 3000

Actual Cost 2000

Percentage Completion = (2000/3000) = 66.67

Accrued Revenue is zero

 

  • Sub Project 2 |

Total Cost 6000

Actual Cost 2000

Percentage Completion = (2000/3000) = 33.33

Accrued Revenue is zero

 

How can we ensure that accrued revenue is estimated on the sub project level as well ? The required of our company is to do the following:

  1. Hours forecast and actuals are recorded on the sub project
  2. Expense forecast and actuals are recorded on the Master project
  3. Invoices to be issues to the client on the master project ( as the project customer doesn't care about all the internal sub projects)
  4. Estimates to be done on the sub project, in order to allocate revenue per sub project

Thanks in Advance,

 

*This post is locked for comments

I have the same question (0)
  • Ahmad_Safadi Profile Picture
    373 on at

    Any feedback ?

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi,

    There is a periodic task for creating estimates available. Meaning that you do not have to do this from an individual project level. Have you tried using this functionality?

    Best regards,

    Ludwig

  • Ahmad_Safadi Profile Picture
    373 on at

    Thanks for the prompt response,

    Yes, I know the utility. Although, my question is primarily about the estimation level.

    Since invoicing and on account transactions are provided on the master level, when I do estimate on the sub project level, accrued revenue is zero.

    Highly appreciate your response,

  • Ahmad_Safadi Profile Picture
    373 on at

    Any feedback ?

    Your advice is highly appreciated,

  • vaasu Profile Picture
    415 on at

    Hi Saf,

    How did you achieve this scenario ,

    can you please let me know

  • Suggested answer
    Vaibhav Sangave Profile Picture
    221 on at

    Hi,

    I had a similar scenario.

    You can either set your milestones at the subproject level or you can use the costs incurred on the subproject to be used in the completion calculation of Master project.

    For eg:

    Master project cost forecast is 10000.

    Cost incurred on master project 1000.

    Cost incurred on subproject 1000.

    If you update estimation project on your subproject as Master project and run estimate on the master your completion percentage is calculated as 20% and revenue is accrued accordingly.

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello A.Saf,

    Want to follow up on this one and ask if there is any other help/information that you need from the community in regards to this issue.

    Best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
CP04-islander Profile Picture

CP04-islander 39

#2
Michel ROY Profile Picture

Michel ROY 14

#3
imran ul haq Profile Picture

imran ul haq 8

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans