I have an issue with Budgeting and Project forecasting.
I've created expense forecast in project and copied it to the ledger. In Budget register entry list, I can see one Line = 500USD
I would like to change one line in expense forecast from 100 USD to 0 USD. I change the amount in line and save it.
After update the line, I copy Expense Forecast to ledger once again. Parameter 'Revers previously transferd' is ON .
After all, budget entry with reverse amount is incorrect, it shows -400USD. I would like to know why it is not 500USD?
Budget entry with new amount shows +400USD an it is OK.
I work with MS D365 FO,10.0.33 version
All tips are welcome :)
Thank you very much for help.
Iza


Report
All responses (
Answers (