Overhead charges are not calculating in bom calculation

(0) ShareShare
ReportReport
Posted on by 3,518

hellow everyone

i am using microsoft dynamics ax 2012 r3 . when i am calculating the bom then there is not showing any overhead charges . i sets the cost sheet setup . am waiting for your suggestions :) .

Thank you 

*This post is locked for comments

I have the same question (0)
  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Paras mehan,

    How did you set up the Overhead charges in your cost sheet?

    Is the overhead charge price active in a costing version?

    Have you saved the costing sheet and are the correct basis groups specified in your costing sheet?

    It would be great if you could attach some screenprints that illustrate how you set up the costing sheet.

    Many thanks,

    Ludwig

  • Paras mehan Profile Picture
    3,518 on at

    yes sir , all the setups are done but not showing overheads still . costing version is done and status is current active in cost sheet .

    20170726_5F00_105951.jpg20170726_5F00_105951.jpg

    and i also want to know that how can i sets the cost of assembly charges .

    Thank you . :)

  • Paras mehan Profile Picture
    3,518 on at

    rate is not working in this , surcharges are working .

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Paras mehan,

    Assembly charges can be incorporated through your route that you use for producing your item. They are linked to categories that have a cost price set up.

    Best regards,

    Ludwig

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Paras mehan,

    Can you compare the calculation basis of the OVH2 and OVH3.

    I can identify a cost Group 'COGM-NO...' from your first screenshot that I cannot identify in your second one because there it says 'NOKIA_CG'.

    Probably this is the thing you overlooked?!

    Best regards,

    Ludwig

  • Paras mehan Profile Picture
    3,518 on at

    hellow sir ,

    i again done all process on new product , now everything is fine assembly charges working but but only one doubt is not clear . which is rate in overhead . current status is activate but not showing in calculation of bom .

    thanks

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi Paras mehan,

    About the overhead rate:

    - can you check whether the basis for the calculation of this rate is set up correctly?

    - Can you check and possibly share the rate that has been set up? Also check that the rate is applied to the correct inventory site.

    Best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Joris dG Profile Picture

Joris dG 5

#2
Alexey Lekanov Profile Picture

Alexey Lekanov 2

#2
Henrik Nordlöf Profile Picture

Henrik Nordlöf 2 User Group Leader

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans