Hi there,
I just want to know if it is possible to update automatically the cost category when the operation resource is changed from the planned production order
I will show you the steps that I follow to change the resource, the result that I getting rigth now, and the desired result.
1. The planned production planned order is created once the master planning is executed.
2. The Gant chart is open, another similar resource is added.
The default route operation resource is EXT-18 (Cost category: CAT EXTRUSOR #18), but it will changed by EXT-10.
3. The resource is changed.
4. The planned prduction order is firmed.
The production order resource is EXT-10,
However, the category cost is CAT EXTRUSOR #18, so, the production order wil be costed with the cost of the EXT-18 and not with the cost of EXT-10.
I want to know if there is a way to update the category cost when the resource is changed.
I really appreciate your help.