Hi Guys,
I have got a Project Service demo environment. I have created a new project and booked some resources. However, I cannot see the effects of these bookings on Resource Utilization view.
This is the Project Team Members associated view. As you see, Hal Matheson is booked from June 15 to August 2.
This is the Resource Utilization view. The booking does not affect the percentages for that resource.

Am I doing something wrong?
*This post is locked for comments
I have the same question (0)