Routes and Schedule Jobs

(3) ShareShare
ReportReport
Posted on by 50
I have a question regarding the scheduling of an order. The order is to be completed by March 9, 2026. The system calculates a “job” time of over two weeks for the completion of 200 components. 
Behind the item number of the component is a route with 120 finished goods per 8-hour shift; we work 5 days a week. 
Why does the system calculate a production time of over two weeks if the required number of units should be completed in 2 8-hour shifts?
How are the two values related? 
I have the same question (0)
  • CU27110933-0 Profile Picture
    2 on at
    Hello!
    The system shows over two weeks because “job time” includes more than the route’s run rate—it adds setup, queue, transfer, calendar limits, and capacity constraints. While the route says 120 units per shift (so 200 units in about two shifts), the scheduling engine calculates total e-zpassritba duration across all operations and resource rules, which stretches the timeline. In short, route capacity is the ideal throughput, while job time reflects the full scheduling reality. 
  • Suggested answer
    PD-13060459-0 Profile Picture
    50 on at
    Thanks for your response! 
    On what basis is the duration calculated? What parameters are included? 
    So far, we have only specified routes.
    When we move production orders, the overview of net requirements always changes completely, and we don't know why...

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 617

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 461 Super User 2026 Season 1

#3
Syed Haris Shah Profile Picture

Syed Haris Shah 298 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans