Hi All,
I am want to change the order date and delivery date in planning order with type is purchase. Automatically values are populated with the same date both order date and delivery date.
How can i change both. how to set our preferably dates.
please guide me.
Regards,
Srinivas
Hi srinivas N.
May you please describe your situation and expectation in more details. Please also with screenshots. The planned purchase orders do have the fields "Delivery date" and "Order date". Both fields are editable. If you are not OK with the pre-filled information from the system you can modify them manually as you need it.
Hi Srinivas,
There are many parameters controlled about this. Order and delivery dates depend on available capacity and lead time setting. Delivery date may be calculated based on multiple demands, such as sales order, demand forecast, production order and safety stock. You can learn more about this and test it in the test environment.
Please refer to below blog.www.ebecs.com/.../master-planning-unplugged-volume-3-reducing-the-noise
QianQW
Hi Christoph Thaler,
Thanks for your information , how can I set as Manually the delivery date and order date.
Just use the "Edit" button and modify the fields as needed.
if you are not able to modify the fields please check your permissions. Maybe you are not allowed to modify them....
Yes, i have try this , actually automatically the date are populated like this.
Order Date : 3/1/2020
Delivery Date (Exp) : 6/1/2020
When I try to change order date both(Order date , Delivery date) are reset to 6/1/2020
I want to change like this order date is 3/25/2020
Delivery Date is 5/25/2020
This is my problem. How can i achieve this.
After you have modified the fields you have to change the field "Status" to approved.
The status of the date, calendar which is assigned the master planning setup.
when you try to take the previous dates it will check the status of the date is closes or not , the date which is given by us active It will consider, if not it consider the next date which is open status.
Regares,
Dear Srinivas,
The Gap between Delivery date and Order Date is calculated automatically based on Purchasing Lead time (In Item default parameters settings).
Purchase Lead time = Default time between confirmed PO and PO delivery date
If the Lead time = 0, so your Order date is equal to the Planned order delivery date.
Best regards.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our 2026 Super Stars!
We are thrilled to have these Champions in our Community!
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Giorgio Bonacorsi 635
André Arnaud de Cal... 592 Super User 2026 Season 1
CP04-islander 356