master planning Issue

(0) ShareShare
ReportReport
Posted on by 2

Hi,

     I have run the master planning for an item and the production lead time of the item is 4 days but it is going up to 1 month.

Analysis:

1. i noticed that there is a Gap between two operations(approx. 25 days gap) which is causing the delay in the production.

2. I have checked the calender and capacity availability and both are available.

3. I have unchecked the find trade agreements check box, So the lead time of the raw material should not be a problem.

has anyone faced the problem?is there anything else that I need to check??

Awaiting your responses!!!Thank you!

 

*This post is locked for comments

I have the same question (0)
  • Julie Johnsey Profile Picture
    570 on at

    Check the queue time or set up time.

  • Weaveriski Profile Picture
    23,620 Moderator on at

    Are you finite scheduled?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Sagar Suman Profile Picture

Sagar Suman 2 Super User 2026 Season 1

#1
Alexey Lekanov Profile Picture

Alexey Lekanov 2

#1
Pratik Bhosle Profile Picture

Pratik Bhosle 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans