Hi,
I have a number of resources that have a main crew but sometimes work with other engineers on single jobs.
I've built another crew however it won't let me add the resource as the engineer is already registered in a crew.
How can I get around this?
Thanks
Hi,
The restrict is that an engineer cannot be added into different crews at the same time period.
So you just need to adjust the From Date and To Date to ensure that one engineer at different crews with staggered time slots.