Hi all,
Can I mark a specific WBS task as "complete" based upon a change on the project record field?
If so, can I accomplish this by using workflows?
Thanks,
Jon
*This post is locked for comments
Hi all,
Can I mark a specific WBS task as "complete" based upon a change on the project record field?
If so, can I accomplish this by using workflows?
Thanks,
Jon
*This post is locked for comments
Yes, you can do this with Custom workflow. you can update WBS task on the update of project field