Actuals against budget not calculated

(2) ShareShare
ReportReport
Posted on by 16
I created and Approved a Cost Budget line with values filled in Task, Role, Resource, Resourcing unit, and Amount. 
I then approve a time entry for the same Task, Role, Resource and Resourcing unit. But when I check the cost actuals I get a message in 'Budget Evaluation Result' that "Budget evaluation could not find a budget line for the dimensions on this actual. This actual will be regarded as unbudgeted spend on the project." 
 
The Budget Match Priorities are as follows. How can I get the actuals calculated?
 
 
I also tried importing the time estimates generated on the project, but it failed with the below error. What am I doing wrong? 
 
""Context is Cost. Transaction class Time.
******************************************************
The resource assignment with Task Planning and Role  could not be imported to budget line because of the following error:
Budget line can't be saved. Amount should be greater than zero.
******************************************************"
I have the same question (0)
  • PhillipsB Profile Picture
    102 on at
    Hello,
     
     - Ensure that the budget line dimensions (Task, Role, Resource, Resourcing unit) match exactly with the time entries
    - Make sure these are set correctly to allow matching
    - Confirm that time entries are correctly associated with the budgeted task and resource
    - Ensure all amounts in your import file are greater than zero to avoid import errors
     
    If mismatches persist, consider running a reconciliation process for your project budget. You can also contact Microsoft Support for further assistance
     
    I think it should help
  • AU-26091724-0 Profile Picture
    2 on at
    I encountered the same import error message and the actual issue was that on my master cost and sales price lists, the roles have a resourcing company associated. This (at least at the time I was testing, ~4 months ago) was my issue- as soon as I removed the reference to the resourcing company on the role price, I was able to import and log actuals against my budget.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 664 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 522 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 303 User Group Leader

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans