Our company is a contract manufacturer that produces several finished goods out of many of the same components.
For example:
It takes A, B, and C to make Z
It takes B and C(x2) to make Y
It takes A, C, and D to make X.
When I run a Forecast Schedule and then a Master Schedule, the system says that I need to produce A, C, X, Y, and Z, but not B. I know that there is no way to create all the A, C, X, Y, and Zs without B.
Can anyone explain what I need to do within AX in order to fix this problem?