I have a client due to go live soon and I had some questions I had around MTD (I haven’t taken a client through to Production for MTD yet)

1. In Sandbox, when creating a new VAT obligation for the next period, I must delete the previous submission to be able to submit a new one. This would not be practical in Production as the client would need to be able to see all historic MTD submissions. 

Is it possible to create a VAT obligation request for the next period without deleting the old one in Production or is there another workaround for this? 

2. How do I obtain the production credentials?  and how long in advance should I be doing this from go live?  

I have the same question (0)
  • Suggested answer
    Sheela Ningappa Profile Picture
    on at

    Hi,

    1. Yes, it is possible to create a VAT obligation request for the next period without deleting the old one in production.

    2. Please find the below link which explains how to obtain production credentials:

    docs.microsoft.com/.../emea-gbr-mtd-vat-integration

    Thanks,

    Sheela

  • James-Mc Profile Picture
    203 on at

    Hi Mia - Can you give more detail on how you are completing multiple test submissions? Once I've completed one I cannot complete another. Even if I delete all the obligation requests all I can do is create new VAT Obligations requests but none result in a New VAT return line being created. Would really appreciate a response.

  • Suggested answer
    Sheela Ningappa Profile Picture
    on at

    Hi James,

    You need to create a new test user  and add the VAt number on Electronic message processing and authorize the web application with new user id and password and then try to create new obligation.

    Thanks,

    Sheela

  • Mia07 Profile Picture
    95 on at

    Hi James,

    The 2 options that worked with me are: 

    1 -  delete submitted lines - basically delete all your line for the previous submission, If the line can not be deleted set the parameter to allow delete in the Message item statuses setup. 

    2 - Generate new test user login details, update your vat number and reset the HMRC connection for you to submit s 2nd submission. 

    Hope that helps 

    Thanks

    Mia

  • Mia07 Profile Picture
    95 on at

    Just to add to the above, the issue with generating a the next submission only happens in Sandbox. In Production you are able to submit as normal.

  • James-Mc Profile Picture
    203 on at

    Thanks Mia and Sheela for both responses - I'll give the first option a go, it would be a real pain to create a new test user every time I want to do a test submission as I'd like to test this multiple times.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Abhilash Warrier Profile Picture

Abhilash Warrier 669 Super User 2025 Season 2

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 449 Super User 2025 Season 2

#3
Martin Dráb Profile Picture

Martin Dráb 384 Most Valuable Professional

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans