RE: Project estimates on contract currency (not company currency)
Hi Gaurangkumar Jani, thanks for your quick reply.
Considering that the contract currency is different than accounting currency, then if devaluation occurs I need to register again same progress on estimation just to recognize that "revenue" (which is actually and exchange rate difference).
Example:
ACC = accounting currency
On-Account transactions = 1000 USD
Run estimates to post 10% progress (Exchange rate with my accounting currency 1 USD = 1 ACC) so 100 ACC are posted.
Next month, exchange rate changes to 1 USD = 1.1 ACC. So when running new estimate at 20% (another 10% progress) new estimation is created for 120 (20% of 1000USD is now 220, not 2000) so as I have already posted 100, now 120 will be posted. However, 10 of that 120 should be allocated to first estimation as it is only exchange rate difference.
Hope I have been clear about my issue.