Notifications
Announcements
No record found.
Check your Work Date.
Dampener Period
Rescheduling Period
Safety Lead Time
Re-run "Calculate Plan" in the Requisition Worksheet after these checks.
Thanks,
KP
Maybe this will help clarify it.
The due date is usually based on the start date you enter in the Calculate Plan request page. The system plans from that date forward, so if your start date is, for example, 06/05/2025, it will schedule the supply for 07/05/2025.
Even if today is 16/05/2025, the system doesn’t automatically use today’s date unless it's set in the filter.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
OussamaSabbouh 2,092
YUN ZHU 663 Super User 2025 Season 2
Sumit Singh 515