Maybe this will help clarify it.
The due date is usually based on the start date you enter in the Calculate Plan request page. The system plans from that date forward, so if your start date is, for example, 06/05/2025, it will schedule the supply for 07/05/2025.
Even if today is 16/05/2025, the system doesn’t automatically use today’s date unless it's set in the filter.
Check your Work Date.
Dampener Period
Rescheduling Period
Safety Lead Time
Re-run "Calculate Plan" in the Requisition Worksheet after these checks.
Thanks,
KP