Project Management and Accounting Forecasting Item cost with average cost method

(0) ShareShare
ReportReport
Posted on by 20

I am having trouble getting an item's average unit cost price default on Project Management and accounting item forecasts. See below for details:

Item's are setup to use the average cost method where the average unit cost is calculated in the Released item > Managed Cost > Cost Objects table per warehouse

pastedimage1588078025759v1.png

In Project management and accounting module, on a project > plan > item forecasts, when I enter the item and warehouse combination for which I have an average unit cost, no unit cost price defaults

pastedimage1588078098474v2.png

My expected results is that the item and warehouse combination with average unit cost should default that cost on the PM&A item forecast line.  Let me know if this is correct and what setups I am missing or if my expectations are incorrect. thanks!

I have the same question (0)
  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello Hector,

    I don't think that your requirement is covered in the standard application.

    You either need to implement a system modification, go along with what you have or suggest a new product idea in the experience/ideas portal.

    Best regards,

    Ludwig

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello Hector,

    Have you reviewed the feedback? Do you need any other help from the community?

    Would be great if you could keep us updated how things are going.

    Many thanks and best regards,

    Ludwig

  • Hector Valdez Profile Picture
    20 on at

    Hey Ludwig, thanks for following up. I suggested the customer add the the cost on the released item > manage cost > price field so that the project can have an item forecast and be able to estimate costs, even if its no the exact average cost for the item/warehouse combination. Thanks for feedback!

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Thanks for your feedback.

    Is there something else the community can help you with?

    If this is not the case then please be so kind and verify the answer to get this thread completed.

    Many thanks and best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 657

#2
André Arnaud de Calavon Profile Picture