Is it possible to schedule a job on multiple resources at a different times?

(0) ShareShare
ReportReport
Posted on by 2,696

Hello Expert,

Resource requirement is specified at the resource group level.

We have a requirement to schedule a job on all the available resources from a resource group so that we meet the delivery date without stretching a time line.

In addition, job can start at a different time on different machine.

Is this something possible to achieve out of the box?

Regards

-Rahul

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Weaveriski Profile Picture
    23,620 Moderator on at

    You would use the number of resources on the route, so if your group had 4 resources and you route said use 4 it would use all of them, use 2 it would use 2 of them. As for the different times that would depend upon load and finite setting I guess, you would need to try it. 

  • Rahul Shah Profile Picture
    2,696 on at

    Hi Steven,

    In our case, we expect number of resources to be used for scheduling depends on their availability.

    In other words, if resource group has 10 resources and if five resources are available today those five should be picked up for the scheduling.

    Having said that, we cannot fix the number of resources at route level.

    Load factor will not work for us either, as machine can be loaded 100 % always provided capacity is available.

    Regards

    -Rahul

  • Weaveriski Profile Picture
    23,620 Moderator on at

    It is the dynamic nature of it you cannot do - you need to tell it how it works to schedule and plan. You cannot say use this "group" and if 5 of 10 are free use 5, it does not do that as standard unless you tell it to use 5. The availability is no issue, it is the use 1-10 resource based upon availability that is the issue. When planning runs your first job would take all 10 leaving every job behind late :-)

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Joris dG Profile Picture

Joris dG 5

#2
Sagar Suman Profile Picture

Sagar Suman 2 Super User 2026 Season 1

#2
Alexey Lekanov Profile Picture

Alexey Lekanov 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans