Is it possible to schedule a job on multiple resources at a different times?

Posted on by 2,692

Hello Expert,

Resource requirement is specified at the resource group level.

We have a requirement to schedule a job on all the available resources from a resource group so that we meet the delivery date without stretching a time line.

In addition, job can start at a different time on different machine.

Is this something possible to achieve out of the box?

Regards

-Rahul

*This post is locked for comments

  • Weaveriski Profile Picture
    Weaveriski 23,616 on at
    RE: Is it possible to schedule a job on multiple resources at a different times?

    It is the dynamic nature of it you cannot do - you need to tell it how it works to schedule and plan. You cannot say use this "group" and if 5 of 10 are free use 5, it does not do that as standard unless you tell it to use 5. The availability is no issue, it is the use 1-10 resource based upon availability that is the issue. When planning runs your first job would take all 10 leaving every job behind late :-)

  • Rahul Shah Profile Picture
    Rahul Shah 2,692 on at
    RE: Is it possible to schedule a job on multiple resources at a different times?

    Hi Steven,

    In our case, we expect number of resources to be used for scheduling depends on their availability.

    In other words, if resource group has 10 resources and if five resources are available today those five should be picked up for the scheduling.

    Having said that, we cannot fix the number of resources at route level.

    Load factor will not work for us either, as machine can be loaded 100 % always provided capacity is available.

    Regards

    -Rahul

  • Suggested answer
    Weaveriski Profile Picture
    Weaveriski 23,616 on at
    RE: Is it possible to schedule a job on multiple resources at a different times?

    You would use the number of resources on the route, so if your group had 4 resources and you route said use 4 it would use all of them, use 2 it would use 2 of them. As for the different times that would depend upon load and finite setting I guess, you would need to try it. 

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Community AMA December 12th

Join us as we continue to demystify the Dynamics 365 Contact Center

New! Quick response templatesâš¡

Save time with the new custom templates!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,151 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 229,993 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans