There is a requirement as below:
- BOM has been setup in BC
- On project planning lines, the end user add the parent BOM item, not the child BOM items.

Hi all,
There is a requirement as below:
- BOM has been setup in BC
- On project planning lines, the end user add the parent BOM item, not the child BOM items.
Set the parent as Assemble-to-Order, which will create an Assembly Order behind the Project Planning Line. There will now be demand for the child BOM items, which will appear in the Req. Worksheet (assuming Planning is configured). When all Items are received, you will post consumption of the Parent Item (pushing from the Project Planning Lines to the Project Journal), which will auto-consume the child BOM items and close the Assembly Order.
Easy, Out-of-the-box solution!
Best Regards,
Ben Baxter
Accent Software Inc