Hi,
I created a trade agreement for purchase price with 2 effectivity dates.
The first effectivity date is dated March 1-31 and the second effectivity date is April 1-April 30.
I created 2 purchase requisitions, one is for delivery in March and the other one is for delivery in April.
My system date is March when I created the 2 purchase requisitions.
During creation of first purchase requisitions, I accepted the default requested date of March and the system pick up the correct purchase price for March.
During creation of 2nd purchase requisitions this time the delivery date is April, I accepted the default requested date which is March and then edited the requested date in purchase lines to April.
Upon checking the unit price, the default unit price is March unit price and not the April unit price as setup in trade agreement.
In order to change the unit price from March to April unit price, I have to re-select the vendor account so that the system will get the correct unit price which is April.
Is it a bug or by design? I'm using D365 F&O.
Appreciate your inputs.
Thanks.