Hi,
I have raised a PO for for the Following
- Item A - 100 Nos
- Item B - 100 Nos
I have done the GRN for the same but instead of Item A i selected Item B
Now i want to do swapping from Item B to Item A ,
Both has the same unit price
please advise
Hi,
I have raised a PO for for the Following
I have done the GRN for the same but instead of Item A i selected Item B
Now i want to do swapping from Item B to Item A ,
Both has the same unit price
please advise
Hi Sriram GS,
All changes that you want to make require adjustment / correction postings.
Unfortunately, there is no shortcut.
Cheers,
Ludwig
Hi ,
Is it possible to swap between the dimensions of the item ie. variants like size, colour etc.
Hi,
Just a suggestion, you can use bom journal. bom line is -100 B and bom header is +100 A
Best Regards
Hi Sriram GS,
You will have to correct the GRN that has been posted and post a new corrective GRN for item B and a correct GRN for item A.
There is no shortcut to 'swap' things.