Individual selection of resources when job scheduling

(0) ShareShare
ReportReport
Posted on by

Hello everybody!

I would like to know if it is possible, and where-how to work this situation in AX 2012.

I have a resource group of 5 resources, a production order was scheduled to be finished by the 5 resources, but when I'm about to start the order, for whatever reason it is decided that this particular order will be produced using only 3 of the 5 resources.

Therefore I should have those 3 resources occupied longer time, and the other two free of capacity if nothing else is assigned to them.

What should I do to reflect this in AX?

Many thanks!

Héctor

*This post is locked for comments

I have the same question (0)
  • Community Member Profile Picture
    on at

    Hi Hector,

    The scenario above is possible in AX. You should work with job scheduling. And you should consult capacity reserve to view as AX has scheduled resources.

    Regards,

  • Hector Cazot Profile Picture
    on at

    Thanks again Murilo, yes I'm working with job scheduling, but AX is scheduling the total quantity of the order using the 5 resources, which is fine for me as the first approach.

    But I want to let two of them absolutely free and do the scheduling in just the other 3 resources at the moment the production order is going to start.

    What should be done to achieve this? I try with manufacturing execution system, I thought I moved on job from one resource to other with the Edit Job List form, but when going back to the production order, and saw the gantt, the 5 resources were still there fully occupied.

  • Suggested answer
    Community Member Profile Picture
    on at

    On the route record, there should be a value for resource quantity you can edit. It's probably showing 5, change to 3, then redo operations and job scheduling.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Joris dG Profile Picture

Joris dG 5

#2
Alexey Lekanov Profile Picture

Alexey Lekanov 2

#2
Henrik Nordlöf Profile Picture

Henrik Nordlöf 2 User Group Leader

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans