Work Order Service Duration Bookings

(0) ShareShare
ReportReport
Posted on by 70

When creating a work order within Field Service, I add in a service called 'Labour' at a duration of 1 hour.

I then want to book that work order to a resource which should calculate the duration at 1 hour, however it ignores any durations entered in a service directly in the work order.

Duration of the service is an hour.

2020_2D00_05_2D00_29-14_5F00_39_5F00_04_2D00_Window.png

When trying to book the work order, it has 0 duration. The only one with a duration of 30mins was an Incident.

2020_2D00_05_2D00_29-14_5F00_39_5F00_04_2D00_Window2.png

Why isn't it calculating any duration on the standard services?

  • SyedM Profile Picture
    on at
    RE: Work Order Service Duration Bookings

    Duration on Primary Incident type is used to show booking duration

  • Thomas David Dayman Profile Picture
    11,323 on at
    RE: Work Order Service Duration Bookings

    You can always create a workflow which creates the Work Order Service tasks when the Work Order Service is created?

  • Paul Deemer Profile Picture
    70 on at
    RE: Work Order Service Duration Bookings

    Thanks, but if you create an opportunity with service products in there that are converted into a work order. How are you suppose to calculate the duration of the work order without any guidance on estimated duration?

    What you've said makes sense but I would also be nice if it could advise the scheduler how long the services add upto.

  • Suggested answer
    Thomas David Dayman Profile Picture
    11,323 on at
    RE: Work Order Service Duration Bookings

    The Work Order Service does not calculate the duration on the Resource Requirement. It is only used to calculate how much to charge on the Work Order.

    You need to add a Work Order Service Task instead. Then this will add on to the duration

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Daivat Vartak – Community Spotlight

We are honored to recognize Daivat Vartak as our March 2025 Community…

Announcing Our 2025 Season 1 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Kudos to the February Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 292,884 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 231,760 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156 Moderator

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans